Uzbekistan: Oversight of First Nuclear Power Plant, Local Content, and Coordination with Kazakhstan
Uzbekistan plans to create a joint engineering enterprise for independent technical oversight of the nuclear power plant under construction in Jizzakh Region and to increase the share of local production in the project. In parallel, Tashkent and Astana agreed on a roadmap for cooperation on nuclear safety.

Sources
· 7Узбекистан предложил создать СП для надзора за первой АЭС
1Узбекистан намерен довести местную долю в АЭС в Джизаке до 30%
2Узбекистан и Казахстан согласовали дорожную карту сотрудничества по ядерной безопасности
3Узбекистан отстраняет Росатом от надзора за строительством АЭС
4Узбекистан исключил Росатом из надзора за АЭС после плана консорциума
5Казахстан нацелился на $4,5 млрд местного содержания для АЭС
6Казахстан подписал контракт с дочерней структурой Росатома на строительство первой АЭС
7Key points
- Uzatom proposed creating a joint engineering enterprise with a foreign partner to inspect the design and equipment and oversee construction quality at the NPP in Jizzakh Region.
- The Government of Uzbekistan plans to increase the share of local production in the NPP project from 21% to at least 30% and create a 200-hectare industrial zone in Forish District.
- Uzbekistan and Kazakhstan agreed on a roadmap for cooperation on nuclear safety and environmental monitoring on August 21.
- In the September 2 presidential statement on the creation of an international consortium, Rosatom was not mentioned even once.
- Kazakhstan previously approved a target of 30% local content in its future nuclear industry before the start of NPP construction.
What happened
The Atomic Energy Agency of Uzbekistan (Uzatom), in a September 4 report, proposed creating a joint engineering enterprise with a foreign partner. The enterprise will inspect the plant's design and equipment and oversee construction quality at the site in Jizzakh Region. Potential foreign participants and the timeline for setting up the enterprise were not named.
The Government of Uzbekistan intends to increase the share of local production in the NPP project in Jizzakh Region from 21% to at least 30%. A 200-hectare industrial zone is planned in Forish District to accommodate at least 100 joint ventures.
Why it matters
Construction of the NPP in Jizzakh Region began on June 4, and the project remains dependent on the Russian contractor Atomstroyexport. Uzbekistan and Kazakhstan are entering nuclear power almost simultaneously: Uzbekistan is building its first plant, while Kazakhstan is planning at least three.
Previously
- Kazakhstan approved a plan to increase the share of local content to 30% before the start of NPP construction, targeting $4.5 billion in local production and contracts.
- Kazakhstan signed a contract with Rosatom's subsidiary JSC Atomstroyexport for the construction of its first 2,400 MW nuclear power plant near the village of Ulken in Almaty Region.
Related original articles
- 18h agoУзбекистан предложил создать СП для надзора за первой АЭСTimes of Central Asia
- 4d agoУзбекистан намерен довести местную долю в АЭС в Джизаке до 30%Times of Central Asia
- Aug 25Узбекистан и Казахстан согласовали дорожную карту сотрудничества по ядерной безопасностиTimes of Central Asia