Almaty lost grid power on August 14, halting the metro, cutting water and mobile service, and triggering 10-point traffic congestion. KEGOC said two hydro generators at Kyrgyzstan's Toktogul hydropower plant tripped, overloading a transit line and splitting southern Kazakhstan from the regional grid. Kyrgyz energy officials said blame cannot be assigned until a joint technical investigation is completed.
Key Facts
- Outages on August 14 affected five districts of Almaty — Bostandyk, Nauryzbay, Auezov, Alatau, and Zhetysu — and 10 districts of Almaty Region.
- Almaty metro passengers were evacuated from tunnels using flashlights and phone screens, and 150 police were redeployed to direct traffic instead of securing the Kanye West concert venue.
- KEGOC reported the disconnection of 500 kV lines L-5300, L-5320 (Agadyr–Ulken) and L-5400 (Aktogay–Taldykorgan), isolating the southern zone of Kazakhstan's unified power system.
- KEGOC later attributed the incident to the trip of two hydro generators at Kyrgyzstan's Toktogul hydropower plant.
- Southern Kazakhstan meets only 50 percent of its electricity demand from local generation, relying on the 500 kV North–South transit and peak-hour imports from Kyrgyzstan.
The Blackout
Power cuts hit Almaty's Bostandyk, Nauryzbay, Auezov, Alatau, and Zhetysu districts at once on August 14. Metro passengers were evacuated from tunnels, lighting their way with flashlights or smartphone screens. Failed traffic lights produced gridlock rated at 10 points on the city's congestion scale. High-rise residents lost water because electric pumps could not lift it, and many lost mobile service when telecom towers went down. Outages extended beyond Almaty to 10 districts of Almaty Region and several other regions of Kazakhstan.
Grid Failure and Attribution
Alatau Zharyk Company said an emergency disconnection of KEGOC's 500 kV overhead lines triggered protective automation and cut consumers in the Almaty region. KEGOC initially reported a technological violation involving lines L-5300, L-5320 (Agadyr–Ulken) and L-5400 (Aktogay–Taldykorgan), which separated the south zone from the Unified Energy System of Kazakhstan. KEGOC's preliminary data pointed to a power surge from the Central Asian unified power system as the cause. KEGOC later clarified that the trip of two hydro generators at Kyrgyzstan's Toktogul hydropower plant overloaded the North–East–South transit and separated the southern zone from the regional grid. Southern Kazakhstan covers about half of its power demand with local generation; the rest comes from northern Kazakhstan over the 500 kV North–South line and, at peak hours, from Kyrgyzstan.
Disputed Responsibility
Kyrgyz energy officials said it is incorrect to blame their power system for all consequences of the accident until a joint technical investigation is completed. Kazakhstan's president warned five years ago that the isolated domestic energy system was unreliable and ordered the government to strengthen the southern zone. The August 14 blackout showed that little had changed, as local energy workers again blamed neighboring countries.