Kazakhstan allocates 384 billion tenge for power plant repairs before winter

2 min
Kazakhstan allocates 384 billion tenge for power plant repairs before winter

This digest was compiled by AI from multiple sources — links to the originals are below.

Kazakhstan has allocated 384 billion tenge for power plant repairs in 2026, a 9% increase from last year, as part of winter preparation. The Ministry of Energy aims to reduce equipment wear to 52% after completing the repair campaign. The program covers 115 units of main equipment, with 50 units already fully repaired.

Key Facts

  • Kazakhstan has allocated 384 billion tenge for power plant repairs in 2026, a 9% increase from the previous year.
  • The repair program covers 115 units of main equipment, including nine power units, 55 boilers, and 51 turbines.
  • As of now, capital repairs are fully completed on 50 units: four power units, 28 boilers, and 18 turbines.
  • The Ministry of Energy plans to reduce average equipment wear to 52% and electrical network wear to 65% after the repairs.
  • The government has allocated an additional 27.9 billion tenge from its reserve for heating season preparation, distributed across three areas.

Repair Campaign Progress

The repair campaign includes capital repairs of nine power units, 55 boilers, and 51 turbines across Kazakhstan's power plants. Capital repairs have been fully completed on 50 units, including four power units, 28 boilers, and 18 turbines. Work is ongoing on three power units, 26 boilers, and 21 turbines. The Committee for State Energy Supervision and Control and its territorial divisions monitor the timing and quality of the repair campaign.

Electrical Grid Upgrades

Capital repairs have been completed on 17,000 kilometers of power transmission lines and 404 substations. The Ministry of Energy expects these measures to reduce average wear of electrical networks to 65%. Deputy Chairman of the Committee for State Energy Supervision and Control, Yernar Khasenov, stated that the main goal is to increase reliability and prevent technological disruptions. In the first seven months of the year, the number of technological disruptions at power plants decreased by 5.6%.

Additional Government Funding

The government allocated 27.9 billion tenge from its reserve for heating season preparation. The funds are distributed as follows: 12.7 billion tenge for repair and construction of heat sources, 8.4 billion tenge for construction and reconstruction of heating networks, and 6.8 billion tenge for reconstruction of electrical networks. The condition of heat sources and networks directly affects the stability of heat supply in cities and settlements.