Kazakhtelecom completes Caspian cable shore infrastructure

AI digest

This digest was compiled by AI from multiple sources — links to the originals are below.

Kazakhtelecom completes Caspian cable shore infrastructure

Kazakhtelecom has completed significant onshore infrastructure for a submarine fiber-optic cable across the Caspian Sea, the company said. The project includes a new coastal station, 7 km of cable ducts, and over 2 km of power lines. The cable aims to boost Kazakhstan's digital connectivity and international telecom routes.

Shore Infrastructure

Kazakhtelecom has fully prepared the coastal landing station (CLS) with a new power complex ensuring reliable electricity supply. Over 2 km of new overhead power lines were laid, and the station's power and cooling infrastructure has been commissioned. More than 7 km of cable ducts were built from the CLS to the shore well, with most of the route passing through difficult soil.

Submarine Cable Progress

Specialists recently completed horizontal directional drilling in the coastal zone for the underwater cable. Construction of the shore well, which will serve as the cable's landfall point, is now finishing. The project's main focus remains on the marine segment, according to the company.

Cable Delivery and Transport

The submarine cable has been delivered to the Kuryk port and subsequently shipped to Azerbaijan via a specialized barge. This milestone was announced by Kazakhtelecom Chairman Bagdat Mussin on his Instagram account.

What's Next

The shore well completion will allow the submarine cable to be pulled ashore. It remains unclear when the marine laying will begin and what the total project timeline is.

2 sources

Kazakhtelecom completes Caspian cable shore infrastructure